It's time for the weekly update!
The foundations are done, and we've let it dry for the rest of the week because the nights have been quite cold. Once the basic frame is built and we'll be able to connect the 3-phase breaker box, the first thing to do is to connect the floor heating system and use it to dry up the concrete for good.
..This is how the entrance looks like now.
..That missing piece between the two blocks of concrete will be done manually.
..The front, those tubes are for cabling and there's also a hidden cableway to the machine room (more like a closet!) running under the floor.
..The back. See that old wooden wall? We've been going forward and backward in ideas whether to keep it or not, but right now it looks like we'll be able to keep it. The wall will be the back wall of those small shelves on the left & right to the triangular bass trap/diffuser. I think it's going to look and feel excellent once cleaned up.
..The machine room to-be. Lots of floor heating cabling there.
.."That's not a ground wire.. THIS is a ground wire."
..Wait, where did all that hay go?
..The fire department didn't show up, even if we did a pretty good effort in smoking the whole neighborhood. The yard looks pretty ugly after all that landscaping, but once we've evened all that ash around and seeded in a new lawn, it's gonna be all green again.
The work with the actual frame starts tomorrow, and I'm really excited to see an actual structure build up.